India's Pumped Storage Plants Hold 7.43 GW Today, 15.87 GW Is Under Construction and 345.38 GW of Sites Are Mapped, With Pinnapuram at 1,680 MW the Biggest Plant
Economy & Infrastructure

India's Pumped Storage Plants Hold 7.43 GW Today, 15.87 GW Is Under Construction and 345.38 GW of Sites Are Mapped, With Pinnapuram at 1,680 MW the Biggest Plant

Illustration by tuput

English

Ten pumped storage plants above 25 MW were running in India as of August 2026, with 7.43 GW between them. Eleven more, totalling 15.87 GW, were being built, and the Central Electricity Authority has mapped 320 sites with 345.38 GW of potential.

· · 9 min read

India had 7.43 gigawatts (GW) of pumped storage running across 10 plants as of August 2026, according to a PIB Research note of 19 October 2026 that draws on the Central Electricity Authority (CEA), the body that plans the country’s power system. A further 15.87 GW across 11 plants was under construction or being implemented, and another 10.40 GW across 8 plants had been cleared or appraised by the CEA. The figures cover plants of 25 MW and above.

A pumped storage plant is a water battery. It uses cheap or surplus electricity to lift water uphill, then lets the water run back down through turbines when power is scarce. This article explains how that works, what India has running and being built, and why the CEA’s figure for mapped sites, 345.38 GW, is far larger than any build plan. It is written as of 12 November 2026.

How a water battery works

The PIB note describes a typical plant as two reservoirs at different heights. When the grid has surplus electricity, water is pumped from the lower reservoir to the upper one, where it stores energy as height. When electricity is needed, the water is released through turbines. The plant’s machines are reversible, so the same unit acts as a pump in one direction and a generator in the other.

Some energy is lost each round. The Pacific Northwest National Laboratory, working for the US Department of Energy, put the round-trip efficiency of a pumped storage cycle at about 80 per cent in a 2023 review. It reached that by multiplying a generation efficiency of 92 to 95 per cent at the upper end by a pump efficiency of up to 85 per cent. The US Energy Information Administration found that American pumped storage plants returned 79 per cent on average in 2019, against 82 per cent for utility-scale batteries. On efficiency alone the two technologies are close.

The difference is how long the stored energy lasts and how long the machine does. The laboratory’s review calls pumped storage unusual among storage technologies for delivering long-duration output, which it defines as 8 to 12 hours, at high power. The Ministry of Power’s reply of 27 July 2026 gives the CEA’s planning figures for 2031-32: 26.69 GW and 175 GWh of pumped storage. Dividing the energy by the power gives about 6.6 hours of full-output running, by tuput’s arithmetic.

The Ministry lists services beyond shifting energy: balancing power, frequency regulation, voltage support and black start capability, which is the ability to restart a grid after a blackout.

Three layouts: on-stream, open-loop and closed-loop

The CEA sorts plants by how their reservoirs relate to natural watercourses. In an on-stream scheme both reservoirs sit on a river, stream or nallah (a seasonal stream). In an off-stream open-loop scheme one reservoir is on a river and the other is not. In an off-stream closed-loop scheme neither is, so the water circulates between two reservoirs away from any perennial stream.

The PIB note says efforts are being made to identify more off-stream sites, to speed up construction and reduce the effect on river life and the surroundings. Of the CEA’s mapped sites, 62 are on-stream with 56.67 GW and 258 are off-stream with 288.71 GW.

Greenko’s Pinnapuram plant in Andhra Pradesh shows how recirculation works. Greenko says on its project page that water is lifted once from the Gorakallu reservoir, part of an irrigation system, and is then recirculated between two new reservoirs, with evaporation losses topped up periodically. Greenko cites an allocation of 1 TMC (a billion cubic feet) for it. Power Technology’s 2023 project profile gives 1.3 TMC for the same project.

The ten plants running today

Renewable Watch lists the ten operating plants, with data as of May 2026, the same 7,425.6 MW that the CEA counts:

  • Pinnapuram, Andhra Pradesh: 1,680 MW
  • Sardar Sarovar, Gujarat: 1,200 MW
  • Tehri, Uttarakhand: 1,000 MW
  • Srisailam Left Bank, Telangana: 900 MW
  • Purulia, West Bengal: 900 MW
  • Nagarjunasagar, Telangana: 705.6 MW
  • Kadamparai, Tamil Nadu: 400 MW
  • Ghatghar, Maharashtra: 250 MW
  • Kadana, Gujarat: 240 MW
  • Bhira, Maharashtra: 150 MW

Pinnapuram’s figure needs a note. Greenko’s project page still describes 1,200 MW for the standalone pumped storage component in the first phase. Greenko’s June 2025 environmental compliance report says the company got its Consent to Operate from the Andhra Pradesh Pollution Control Board on 3 May 2025, and that an amendment raising the plant from 1,200 MW to 1,680 MW, with six 240 MW units and two 120 MW units, had been recommended by the expert appraisal committee. The CEA list, as carried by Renewable Watch, counts 1,680 MW.

Tehri, run by THDC India Limited, completed its fourth unit in April 2026. THDC calls it India’s first variable speed pumped storage plant. A variable speed unit can change how fast it spins, which lets it adjust its pumping power to the electricity on offer. PTI reported in November 2025 that it uses the existing Tehri and Koteshwar reservoirs as upper and lower basins, with four reversible 250 MW units in an underground powerhouse and a head variation of nearly 90 metres. Renewable Watch reported on 13 April 2026 that the fourth unit commenced operation on 12 April 2026.

Bhira in Maharashtra is the smallest plant on the list. Tata Power says it commissioned a 150 MW pumped storage project there in 1997 and calls it the first of its kind in Asia. NS Energy’s 2003 survey gives 1995 for the same unit and says its maximum gross head is 515 metres. The same survey says the first pumped storage in India went in at Nagarjunasagar between 1980 and 1985, as seven 100 MW units, and that the plant has run in ordinary hydro mode because it lacks a tail pond dam. The sources therefore disagree on which was first and when Bhira began. Bhira’s conventional station dates to 1927, a story told in the article on Jamsetji Tata and the hydro scheme.

Renewable Watch lists Tehri at 1,000 MW and Pinnapuram at the top, so Tehri is not the largest. Saur Energy’s February 2026 article on the CEA’s count as of 31 December 2025 notes that the operating total includes Sardar Sarovar, which it says is currently not operational.

The eleven being built

The Ministry of Power’s list of 20 July 2026 gives the executing agency and the target month for each of the 11 plants under construction, 15,870 MW in all:

  • Saidongar-1 Karjat, Maharashtra (Torrent Energy Storage Solutions): 3,000 MW, December 2029
  • Sharavathy, Karnataka (Karnataka Power Corporation): 2,000 MW, May 2032
  • MP30 Gandhi Sagar, Madhya Pradesh (Greenko): 1,920 MW, December 2026
  • Saundatti, Karnataka (Greenko): 1,600 MW, December 2027
  • Bhavali, Maharashtra (JSW Energy): 1,500 MW, December 2028
  • Tarali, Maharashtra (Adani Renewable Energy): 1,500 MW, June 2029
  • Upper Sileru, Andhra Pradesh (APGENCO): 1,350 MW, February 2029
  • Bhivpuri, Maharashtra (Tata Power): 1,000 MW, February 2029
  • Gandikota, Andhra Pradesh (Adani Renewable Energy): 1,000 MW, March 2029
  • Kundah, Tamil Nadu (TANGEDCO): 500 MW, February 2027
  • Chitravathi, Andhra Pradesh (Adani Renewable Energy): 500 MW, February 2027

By tuput’s addition, the four Maharashtra plants total 7,000 MW, which is 44 per cent of the 15,870 MW. The dates are the executing agencies’ targets as listed by the Ministry, not commissioning dates.

Why 345.38 GW of sites is not a build plan

The CEA’s identified potential is 345.38 GW across 320 sites, per the PIB note. The Western region holds 129.72 GW, of which Maharashtra has 67.36 GW and Gujarat 33.36 GW, figures the CEA attributes mainly to the terrain and the steep gradients of rivers rising in the Western Ghats. The Southern region has 97.76 GW, the Eastern 53.41 GW (Odisha 41.53 GW), the Northern 50.32 GW and the North East 14.18 GW.

Other published figures are smaller because they were taken earlier. Saur Energy’s report on the CEA’s count as of 31 December 2025 gives about 267 GW, and traces the series: 97.6 GW at the end of 2022, 124.3 GW in 2023, 183.3 GW in 2024. Renewable Watch gave 290.4 GW as of May 2026. The Saur Energy report says most of the growth comes from newly identified off-stream closed-loop sites, which developers largely identify themselves, and that the total remains dynamic.

The build target is smaller. The PIB note says the CEA’s roadmap envisages 100.81 GW commissioned by 2035-36, including plants already under construction, which would take cumulative capacity to 105.56 GW. Powerline reported the roadmap on 4 February 2026 as 100 GW by 2035-36. Today’s 7.43 GW is about 2 per cent of the mapped potential, by tuput’s arithmetic.

What the government changed

The Ministry of Power’s statement of 20 July 2026 and the PIB note list the steps:

  • Guidelines to promote pumped storage projects, notified on 10 April 2023.
  • Tariff-based competitive bidding guidelines for buying storage capacity from pumped storage plants, notified on 6 February 2025.
  • A 100 per cent waiver of inter-state transmission charges for 25 years from commercial operation, under a CERC notification of 26 June 2025, for projects whose construction is awarded on or before 30 June 2028.
  • Budget support for roads, bridges, railway sidings, ropeways, communications and the transmission line to the nearest pooling point.
  • A shorter wait for the CEA to concur with a detailed project report, down from 90 days to 50, with no inter-state clearance needed.
  • A gazette notification of 1 August 2025 raising to Rs 3,000 crore the project cost above which the CEA must concur, and exempting off-stream closed-loop schemes from that concurrence whatever their cost.
  • Environmental appraisal under the lighter B2 category since 18 May 2023, with one season of baseline data for closed-loop schemes.

Where the counts differ

The PIB note says global pumped hydro stood at 159.8 GW at the end of 2025, per the International Renewable Energy Agency (IRENA), with China at nearly 66 GW, Japan about 22 GW, the United States about 19 GW and India fourth at 7.18 GW. The International Hydropower Association (IHA), in its 2026 outlook of 24 June 2026, gave 201 GW worldwide at the end of 2025 and called the 11.7 GW added in 2025 a record. The IHA’s release describes India’s current capacity as about 3.5 to 5 GW, below the CEA’s count. The pages read for this article do not explain the gaps between these figures.

For how storage is being paid for, see the article on the Rs 14,500 crore Cabinet scheme for 92 GWh of storage, which sets aside 60 GWh for pumped hydro. India’s non-fossil capacity, the reason the storage is needed, is covered in the 300 GW milestone. The earliest target on the Ministry’s construction list is December 2026, for the 1,920 MW MP30 Gandhi Sagar plant.

Share
Copied!

Sources & further reading

  1. PIB Research: Pumped Storage Hydropower, Powering India's Clean Energy Transition (19 October 2026)
  2. PIB, Ministry of Power: Status on Pumped Storage Projects (20 July 2026)
  3. PIB, Ministry of Power: Grid Stability and Energy Storage (27 July 2026)
  4. Greenko AP01 IREP: Environmental Compliance Report for the Pinnapuram standalone pumped storage component (June 2025)
  5. Greenko AP01 IREP Private Limited: Pinnapuram project page
  6. Power Technology: Pinnapuram Integrated Renewable Energy Project, India (21 April 2023)
  7. Tata Power: Pumped hydro storage
  8. NS Energy: Picking up the pace (1 February 2003)
  9. THDC India Limited: India's first variable speed pumped storage plant (Tehri PSP)
  10. Outlook Business (PTI): THDC India looks to fully operationalise 1,000 MW pumped storage project in Jan 2026 (26 November 2025)
  11. Renewable Watch: THDC commissions fourth 250 MW unit of 1 GW Tehri PSP (13 April 2026)
  12. Renewable Watch: PSP progress, key developments, industry trends and deployment across states (28 July 2026, updated 1 October 2026)
  13. Saur Energy: India's PSP potential touches 267 GW as off-stream projects gain momentum (2 February 2026)
  14. Powerline: CEA issues roadmap to 100 GW of pumped storage projects by 2035-36 (4 February 2026)
  15. Pacific Northwest National Laboratory for the US Department of Energy: Emerging Technologies Review, Pumped Storage Hydropower (PNNL-34458, June 2023)
  16. US Energy Information Administration: Utility-scale batteries and pumped storage return about 80% of the electricity they store (12 February 2021)
  17. International Hydropower Association: Year of the water battery, global pumped storage capacity surpasses 200 GW (24 June 2026)
  18. Energy Global: India targets 100 GW pumped storage boom in major clean energy push (24 June 2026)

Researched and written with the help of AI tools and edited for accuracy. Provided for general information and discussion only, not professional advice. See our editorial standards and disclaimer. Spotted an error? Tell us.

#pumped storage#energy storage#hydropower#central electricity authority#renewable integration#pinnapuram#tehri#ministry of power

Enjoyed this? Get the next one.

One good read at a time, straight to your inbox. No spam, unsubscribe anytime.

More in Economy & Infrastructure
The Cabinet Approved Rs 14,500 Crore on 4 November 2026 to Support 92 GWh of Grid-Scale Energy Storage, 60 GWh of It Pumped Hydro
How the money is meant to work, which pumped hydro plants are already under construction, where the 411 GWh planning figure comes from, and why published counts of today's battery capacity do not match.
The Bhakra Dam Rises 225.55 Metres From Its Deepest Foundation, Was Dedicated on 22 October 1963, and Supplies Sutlej Water to Three States and 1,415 Megawatts From Two Power Houses
From a note written on a river tour in 1908 to a canal opening in July 1954 and a dedication in October 1963, the record on Bhakra is detailed. Here are the dates, the dimensions, the shares and what independent studies found on the farms and the families.
Hirakud Dam Was Opened on 13 January 1957 With a 4.8-Kilometre Main Dam, a 743-Square-Kilometre Reservoir, Irrigation in Four Districts and Flood Cover for 9,500 Square Kilometres of the Mahanadi Delta
Tuput sets the dates, dimensions and costs side by side, notes where Odisha's own records disagree with each other, and records what the dam delivers and what it asked of the villages beneath its reservoir.